GENERAL SITE INFORMATION, CHARACTERISTICS, AND STATUS
Project Name: |
NEW BEDFORD HARBOR - PROJECT 1 (Hot Spots)
ProjectID: 01-02 |
Last Updated: |
09/14/98 |
City: |
New Bedford |
County: |
Bristol |
State: |
MA |
Country: |
USA |
Bodies of Water: |
Acushnet River Estuary; New Bedford Harbor (Upper Harbor) |
US EPA Region: |
I |
Status (Active, Complete, or Monitoring Only): |
Complete |
Date On NPL: |
1983 |
ROD/ESD Date: |
1990 (OU-1); 1992 (ESD); 1995 (ESD) |
Operable Unit: |
OU-1 |
Areas of Concern (length or acres): |
Five acres of hot spots in the estuary. |
Other Characteristics of Water Body: |
Four areas containing elevated sediment PCB concentrations in
the Acushet River estuary (greater than 4,000 ppm) were identified. These
"hot spots" totaling five acres are proximal to the New Bedford shore, where
the Aerovox Corporation is located.
The Wood Street Bridge connects the city of New Bedford with the town
of Acushnet. Hot Spot "A", which is contiguous with the shoreline at the
Aerovox plant, covers 1.72 acres and is 1,202 feet south of this bridge.
Area "B" encompasses 2.6 acres of sediment off the New Bedford shoreline
and is situated 2,090 feet south of the Wood Street Bridge. Areas "C"
and "D" are located 2,300 feet south of the Wood Street Bridge and encompass
0.2 and 0.4 acres, respectively. During the design of the remediation
for the "hot-spot" area, further sampling was conducted to more accurately
define those areas with sediment PCB levels greater than 4,000 ppm. Six
Hot-Spot areas were delineated. Hot Spots "A" and "B" were essentially
divided generating two additional "hot-spot" areas. Wetlands are located
in the region encompassing the "hot-spots" on the Acushnet shoreline,
immediately east of the Aerovox plant.
The Acushnet River estuary which contains the "hot-spot" areas is a 230
acre region that extends from the Wood Street Bridge to the Coggeshall
Street Bridge, 1.6 miles south. A wetland area is situated in the estuary
on the Acushnet shoreline approximately 2,500 feet south of wetlands area
I.
|
Contaminants of Concern: |
PCBs (1016/1242/1254); metals |
|
|
Source of Contamination: |
Discharges from two capacitor manufacturing facilities located
on shoreline. |
Contaminated Area Physical Characteristics: |
10,000 cy of hot spots (4,000 - 200,000 ppm PCBs and 0 - 4,000
ppm metals) |
Type of Regulatory Action: |
Interim Remedial Action under Superfund. Fund-lead. |
Overall Status Summary: |
Dredging of 5 acres of hot spots (OU-1), was completed in 1995,
which took 16.5 months for 14,000 cy to be removed. The dredged materials
have been stored since that time in a nearshore CDF pending selection of
a treatment technology. (Originally, onsite incineration was planned, but
was canceled due to public opposition three months after hot spot dredging
started.) A proposed ROD Amendment issued for comment in August 1998 rejects
treatment |
REMEDIAL ACTION IMPLEMENTED
Project Name: |
NEW BEDFORD HARBOR - PROJECT 1 (Hot Spots)
Project ID: 01-02 |
Last Updated: |
09/14/98 |
Physical Target: |
5 acres of hot spots in the estuary (defined as >4,000
ppm PCBs). |
Goals: |
Removal to <4,000 ppm PCBs and storage in CDF, pending
treatment. |
Primary Contractor: |
Perland Environmental Technologies, Inc. (subsidiary of Perini). |
Other Contractors: |
AGM (dredging contractor), Metcalf & Eddy (wastewater
treatment plant design), Foster Wheeler (treatment technology testing and
dewatering/disposal). |
Generic Remediation Method: |
Hydraulic dredging. |
Equipment: |
Hot spots dredged using Ellicott 370 12-inch cutterhead; use
of silt curtains abandoned; high suction rate and slow auger rotation emphasized
to control resuspension; pumped from dredge through floating pipeline (up
to one mile) and deposited in nearshore CDF. |
Material Handling: |
As described above ("Equipment:"). |
Volume Removed: |
14,000 cy |
Calender Time: |
Hot spot removal from April 26, 1994 through September 6,
1995. Modifications to CDF and construction of water treatment facility
had started in August 1993. |
Time To Implement: |
16.5 months |
Total Cost: |
$20.1 million, which included both the construction of a nearshore
CDF and a dedicated 350 gpm wastewater treatment plant; $1,430 per cy. |
Dredging Cost: |
$1.74 million; $124 per cy |
|
|
Disposal of Sediment: |
The ROD was amended to allow storage in the project-specific
nearshore CDF for up to 5 years. Testing of treatment technologies was performed
from 1995-1998. Original plan to incinerate onsite abandoned by EPA on 7/12/94
due to public opposition. ROD amendment proposed in August 1998 selects
dewatering followed by offsite disposal at a permitted hazardous waste landfill
as the disposal method for the 14,000 cy. Estimated cost is $14.8 million.
Treatment technologies which were rejected included solvent extraction,
thermal desorption, and vitrification each of which would have taken 4 to
5 years to implement with estimated costs ranging from $19 million (thermal
desorption) to $48.5 million (vitrification). |
Volume of Water: |
160 million gallons treated. |
Method of Water Treatment: |
Water treatment by settling, flocculation, sand filter, micro
(fiber) filters, and UV/oxidation. WWTP design capacity reportedly 350-400
gpm. |
Water Discharge Limit: |
The discharge limit was 0.6 ppb PCBs expressed as a monthly
average. The limit was set based on a) producing no degradation in the Acushnet
River and b) analytical limitations. The analytical limitations are based
on the achievable quantitation limits for the two aroclors in question (quantitation
limits of 0.3 ppb each, or a total of 0.6 ppb). The aroclors are 1242 and
1254.
The discharge limits for the treated water are defined in a permit which
is set up like an NPDES permit, with maximum instantaneous limits and
monthly average limits for both PCBs and metals (cadmium, chromium, copper,
and lead). In order to set water discharge limits that would meet the
"no degradation in the river" requirements, EPA established background
water levels prior to dredging by means of a monitoring program. It's
interesting to note that the water discharge was not required to satisfy
ambient water quality criteria (AWQC) since the hot spot dredging program
was categorized as an interim measure (e.g., hot spot levels may only
be reduced to 4,000 ppm from an initial 4,000 - 200,000 ppm range).
Reportedly, PCB discharge limits were consistently met but copper limits
(monthly average) sometimes proved difficult to meet.
|
Air Monitoring During Remediation: |
Air Monitoring for PCBs (Source: References A- 126)
- Volatilization of PCBs aggravated at this site due to (1) exposed
hot spot areas at low tide and (2) oil slick forming on water during dredging.
- Air sampling locations: ten (four near CDF; six near hot spot)
- Air samples are collected (filtered) over 8-24 hour period; 72-hour
lab turnaround
- Massachusetts Ambient Air Limit: 0.5 ng/m3 (1 ng = 10-9 gm)
- Average background near hot spot: 40 ng/m3
- Average background represents 8 x 10-5 increased lifetime carcinogenic
risk
- Shut down Level: (NIOSH, 40 hr/wk, 50 yrs): 1000 ng/m3
- Action Level (one-half NIOSH): 500 ng/m3
- Notice Level: set at average of four previous background levels plus
30 ng/m3 (represents increased carcinogenic risk of 0.3 x 10-6)
Some results from the first 3 months of dredging, quoted from Reference
E-8:
"The notice level was initially 76 ng/m3 at the start of dredging in
April and was increased to 172 ng/m3 as of June 24, 1994."
"During the first 3 full days of dredging the "notice level" was exceeded
on each occasion with averages of 252, 133, and 134 ng/m3 being measured
with a reading of 825 ng/m3 at the sampler closest to the dredge. This
resulted in modifications to the dredging procedures. Since that time,
the notice level was slightly exceeded on only 4 occasions. The monthly
averages for the dredging area are shown below:
- Month/Year: April 1994; Range (ng/m3): 54-252; Average (ng/m3): 143
- Month/Year: May 1994; Range (ng/m3): 21-163; Average (ng/m3): 69
- Month/Year: June 1994; Range (ng/m3): 62-158; Average (ng/m3): 101"
"Monitoring in 1994 at the CDF did not result in modifications to
operations although it highlighted the need for the floating cover on
CDF Cell #1. On several occasions, readings of 1,800 ng/m3 (24 hour sample)
have been recorded at an individual sampler during periods when the cover
was partially removed for maintenance."
|
Water Monitoring During Remediation:
|
Resuspension Monitoring (Source: References A-126)
- Four sample locations in river/estuary: at WWTP discharge; 200' from
dredge; at Coggeshall St. bridge; at Hurricane Barrier
- Five liter water sample; expose to biota in lab (toxicity test)
- Dissolved/suspended PCBs analyzed on 24 hr. turnaround; compared to
pre-determined background
- Criterion: produce no increased impact at Coggeshall St. bridge
- Initial frequency was every day for first 21 days; no increased impact
observed (i.e., none discernible separate from overall impact of estuary
- wide contamination); frequency reduced to once or twice per week;
is periodically increased when moving into more highly-contaminated
areas
- Two factors limit observable effects from resuspension, namely:
- Tide is incoming for 50% of the dredging period; and
- Operating with high suction rate and slow cutter rotation.
- Discharge from WWTP: Refer to summary under "Water Discharge Limit"
References E-8 and E-47 present data on resuspension during the hot spot
dredging. Results collected at the Coggeshall St. Bridge are presented.
The bridge is one mile downstream from the southernmost of the hot spots.
The two references present data that show that the average PCB flux measured
at the bridge during dredging ranged from 0.12 to 0.45 kg/day (0.26 to
0.99 lb/day), a factor of 2-10 higher than pre-dredging.
|
Outcome: |
Achieved the less than 4,000 ppm PCBs target based on a relatively few
post-dredging sediment verification samples collected in dredged areas.
Fifteen final composite samples were used to document post dredge PCB
levels in the 5 acres of hotspot areas. The 15 samples ranged from 67
to 2,068 ppm PCBs with a median of 707 ppm.
|
Restoration and Post-Monitoring:
|
Reference A-334 (1997, circa) describes pre-and post-hot spot dredging
monitoring as follows:
"Prior to initial remedial activities, a comprehensive long-term monitoring
program was developed to assess the effectiveness of dredging at this
site, both spatially and temporally. Pre-remedial baseline sediment sampling
consisted of quantifying a suite of exposure indicators (PCBs, metals,
sediment toxicity), habitat indicators (TOC, AVS, grain size) and ecological
indicators (benthic community indices) at each of 72 stations along a
gradient from the severely contaminated upper estuary to Buzzards Bay.
Recently, the first phase of remediation was completed, dredging of a
five acre "Hot Spot" and the full suite of indicators were measured again.
Pre- and post-dredging comparisons were made for each indicator and are
presented in GIS format. This approach will be used during each remedial
phase, as well as after completion of all remedial activities, to assess
ecological recovery at this Superfund site."
"Sediments were collected before any remedial activities (1993) to establish
baseline conditions. First post-remedial sampling was conducted immediately
after initial "Hot Spot" dredging (1995).
Three of the fmdings in Reference A-334 are quoted below:
- (Based on before and after samples at 72 stations). . . "A significant
PCB contamination gradient exists from the upper to lower harbor. While
any major redistribution of contaminated sediments from the Hot Spot
dredging was confined to the immediate vicinity of remedial activities,
there is evidence that low molecular weight PCBs migrated greater distances.
This newly redeposited material is different in composition from either
Aroclor 1242 or 1254, the predominant Aroclors at the Hot Spot, and
may be the by-product of dechlorination occurring in the Hot Spot sediments."
- "Increased contaminant concentrations (e.g., PCBs, Cu) in 1995 were
observed primarily in the upper harbor.
- Corresponding increases in short-term acute sediment toxicity also
were measured in the upper Harbor."
- "Smaller increases in 1995 contaminant concentrations and sediment
toxicity occurred in lower harbor depositional areas."
The Upper Harbor is about 1.5 miles long and occupies roughly 230 acres.
As presented in Reference A-334, the mean total PCB concentration in the
Upper Harbor (24 sampling stations) was 94 ppm in 1993 (pre-dredging)
and 124 ppm in 1995 (post-dredging). Sediment samples were grabs of the
top two centimeters. This overall mean average PCB surface concentration
increased 32% in the Upper Harbor following dredging.
In Reference C-271, results of air, soil, and produce samples collected
up-and down-wind from the hot spots both pre (1992) and during dredging
(fall 1994) are reported. One of the findings is quoted below.
"A significant increase in PCB concentrations was found in samples of
tomatoes grown during a summer of harbor dredging compared to those from
the pre-dredge period. Downwind of the harbor (site A), PCB concentrations
in tomatoes grown during dredging exceed the concentrations in pre-dredging
samples by a factor of 6."
|
Site-Specific Difficulties:
|
Dredging limited to a 4 to 6 hour daytime window on either side of high
tide, to ensure sufficient water depth to float the dredge.
Four to six hours of dredging at a suction rate of 2,100 gpm would "max-out"
the WWTP for 24 hours. Even without the dredging being tide-limited, this
factor would have limited the hours of daily dredging.
Excessive PCB volatilization to air caused numerous exceedances of PCB-in-air
limit -- resulting in numerous temporary shutdowns of dredging.
As described in Reference E-8, dredging operations brought a layer of
PCB oils to the surface, causing elevated PCB-in-air levels. As a result,
the following dredging modifications were made:
- the dredge's swing speed was reduced to the slowest speed the operator
could maintain;
- the dredge was also stopped at times and used to pull oil off the
surface;
- a shroud was fabricated at the site and installed over the cutterhead
to catch oil as it was released, allowing it to be pulled into the dredge;
- 3 swings were made in an attempt to remove a 1.5 foot lift of material
prior to advancing the dredge; and
- the silt curtains were removed because they appeared to be contributing
to the oil problem by their continuous disturbance of the bottom in
the varying tidal and weather conditions.
|
Monitoring Data References: |
|
|
|
|
|