|
Chlorinated Solvents |
||||||
Installation Date: Contaminants: Reactive Media: Cost: Construction: Point of Contact: |
|
Full-scale permeable reactive barrier (PRB) systems have been installed to treat contaminated ground water at three sites at the U.S. Department of Energy's Rocky Flats Environmental Technology Site (RFETS) in Golden, CO. These projects were a cooperative effort between RFETS and the Department of Energy (DOE) Subsurface Contaminant Focus Area, with support from U.S. EPA's National Risk Management Research Laboratory. The ground-water collection system for the East Trenches Plume PRB system extends approximately 1,200 ft. To install the collection system, an excavation was dug at a variable depth of approximately 16-26 ft below ground surface, at least 6 in and an average of 3 ft into claystone. The barrier was installed on the downgradient side of the excavation and consists of 80-mil high-density polyethylene (HDPE) panels fitted with an interlocking strip on each side. The trench was backfilled with sand and includes a perforated HDPE ground-water collection line that was placed on the sand, and piped to a central collection sump. The collected ground water then flows by gravity from the collection sump through a 2-in, non-perforated HDPE line to the two treatment cells. Each treatment cells is approximately 12 ft in diameter and 13 ft tall. Ground water enters the cells at the top and percolates through the 6.5 ft of iron. There is 1 ft of granular material on the bottom of each treatment cell to disperse the ground water. The upper foot of each cell is a 50/50 mixture of iron and pea gravel to simplify mechanical break-up of the expected crust formation. Results have shown that, with the exception of methylene chloride, concentrations of VOCs are routinely non-detectable in the effluent samples.
Lessons learned to date from these installations include the following: (1) during construction, the length of trench open must be minimized to reduce slope failure, (2) equipment operations and stockpiling adjacent to open trenches must be minimized, (3) maintenance must be considered in a PRB's design, (4) backfill specifications must be rigidly followed, (5) gravity flow is most effective when the natural contours of a hillside can be utilized; and (6) cost estimated for this system are about one-fourth of the estimated baseline “pump-and-treat” costs. |
Sponsored by the Technology Innovation Program
Date Last Modified: June 1, 2001