|
Chlorinated Solvents |
||||||
Installation Date: Contaminants: Reactive Media: Cost: Construction: Point of Contact: |
|
A full-scale permeable reactive barrier (PRB) system was installed in 1998 to remediate chlorinated aliphatics in a shallow aquifer at the Copenhagen Freight Yard, Denmark. Degreasing agents, including trichloroethylene (TCE) and possibly perchloroethylene (PCE), were used in train repair operations on the site. The upper aquifer contains chlorinated aliphatics in concentrations up to 4,000 µg/L. Although cis- and trans-1,2-dichloroethylene (DCE) are the dominant contaminants due to dehalogenation in the aquifer, PCE, TCE, and vinyl chloride (VC) also are found. Up to 3,000 µg/L of cis-1,2-DCE and up to 700 µg/L of trans-1,2-DCE are present. The local geology consists of a top layer of 6.5 ft of sandy fill underlaid by 3.3-6.6 ft of clayey fill mixed with peat. Below that is 6.5-10 ft of marine coastal sand, which acts as a local upper ground-water aquifer with a piezometric head about 8 ft below ground level. The sand is underlaid by 3.3-6.6 ft of clayey till followed by 20 ft of silty, fluvial sand in hydraulic contact with Danien limestone, which acts as a regional ground-water aquifer. The permeability of the upper aquifer is 0.00019 ft/s, and the average linear velocity of the ground water is about 0.36 ft/day. The PRB system is about 50 ft long, 20 ft deep, and 3 ft thick. During construction of the PRB, sheet pilings were installed first, and the area inside was excavated to form a continuous trench that was backfilled with 83 short tons of Fe0. The top of the PRB is 8.2 ft below ground and is covered with a layer of geotextile, compacted clay, gravel, and pavement on top. The PRB was installed to cut off that part of the plume where the total concentration of chlorinated aliphatics exceeds 100 µg/L. The PRB design was chosen due to cost and availability of construction techniques in Denmark. Design and installation costs are not available at this time. Sampling has been completed. To date, the PRB has effectively treated upgradient concentrations of chlorinated aliphatics above 650 µg/L, bringing them below 10 µg/L downstream. Total chlorinated solvents reduced in the PRB from greater than 1,000 µg/L to less than 50 µg/L, which represents about a 95% reduction.
Precipitation leading to decreased permeability of the PRB may occur in ground water containing high concentrations of inorganic compounds. In the Freight Yard PRB, the total dissolved solids decreased with about 600 mg/L passing though the wall. If the permeability of the Freight Yard PRB continues to decrease, the efficiency of the PRB also may decrease with time. |
Sponsored by the Technology Innovation Program
Date Last Modified: May 30, 2001