Title: The Results of a Zero Valence Metal Reactive Wall Demonstration at Lowry AFB, Colorado
Author(s): Gallant, William A.; Brian Myller
Citation: Air & Waste Management Association's 90th Annual Meeting & Exhibition, 8-13 June 1997, Toronto, Ontario, Canada, 1997.
Abstract: An innovative technology demonstration was implemented at Lowry AFB in December 1995. A 10 foot wide reactive iron section flanked by 14 foot long sheet piling wing walls formed a funnel-and-gate system to treat dissolved chlorinated compounds, with trichloroethene representing the highest contaminant concentrations. In addition to the contaminants, the parameters being measured include Eh, pH, akalinity, DO, conductivity, and turbidity. Monitoring results and the conclusions of the demonstration are presented in a detailed analysis.
 
Title: Reactive Walls Demonstrated
Author(s): Muza, Richard
Citation: Ground Water Currents. April, No. 24, 1997 (Available through http://clu-in.org)
Abstract: A permeable reactive wall was installed at Lowry Air Force Base, CO as part of a funnel-and-gate system. Trichloroethylene (TCE) in ground water is being degraded in situ through a reductive dechlorination reaction involving zero-valent iron.
 
Title: Zero Valence Metal Reactive Wall Demonstration, Project Results and Lessons Learned.
Author(s): Gallant, William A.
Citation: Superfund XVIII Conference, Washington, D.C. December 1-4, 1997.
Abstract: An update of the results of monitoring of the reactive iron wall after 18 months of operation are presented.
 
Title: Final, Evaluation of Long-Term Performance, Reactive Wall Demonstration Project, Lowry AFB
Author(s): Versar, Inc.
Citation: AFCEE, Brooks AFB, TX, December 1997 (Available through Defense Technical Information Center or National Technical Information Center)
Abstract: This report presents the long term (18months) performance evaluation of the reactive wall located at Lowry Air Force Base, which was installed to treat TCE contaminated groundwater. The performance evaluation is based on groundwater monitoring and analysis of cores collected from the reactive wall.
 
Title: Final, Reactive Wall Demonstration Project Technical Report, Lowry AFB, Colorado.
Author(s): Versar, Inc. / Dames & Moore
Citation: AFCEE, Brooks AFB, TX, September 1997. (Available through Defense Technical Information Center or National Technical Information Center.)
Abstract: This report describes the process, design, construction, and performance of a passive in-situ reactive wall installed at Lowry AFB to remediate groundwater contaminated by chlorinated hydrocarbons. This information is used to demonstrate the applicability of the technology to remediate groundwater at Air Force facilities.
 
Title: Final, Evaluation of Long-Term Performance, Reactive Wall Demonstration Project, Lowry AFB, Colorado
Author(s): Versar, Inc.
Citation: AFCEE, Brooks AFB, TX, 1997
Abstract: Abstract currently unavailable.
 
Title: Final, Reactive Wall Demonstration Project Technical Report, Lowry AFB, Colorado
Author(s): Versar/Dames and Moore
Citation: AFCEE, Brooks AFB, TX, 1997
Abstract: Abstract currently unavailable.